We would like create automatic schedule lines based on Release of Production Orders.
We are getting requsitions, but not sure as how to proceed with those requesitions to do a GR
Have maintained ME31l, but left the ME38 / ME84 empty
In routing - Maintained the external operation with Outline agreement #.
Res/ Pur Req = 3 setting
and it generates a purchase requsition!
Is the Purchase requsition needs to be converted into schedule lines?
ME59 is not picking them up.
Any help be appreciated.