Follow-Up material items in MRP4 View

$
0
0

Hi All,

 

In MRP4 view, in discontinued part, if we set follow-up material, MRP will trigger requests for the follow –up material if the stock of existing material is zero.

Now there is a requirement, so that even though follow-up material is updated, system should be trigger any requirement for the existing one, though the stock is zero, ie, the follow up material is only for an information .

 

Is it possible ? can we do it with  changing the effectively of date in eff.out (set it as future unlimited)

 

Thanks for the help.

 

Regards,

  Vijesh